The entry-level method of industrial risk analysis: systematically identify the hazards of a facility, rate the scenarios and flag those that deserve a more detailed analysis.

1What is a PHA?

The Preliminary Hazard Analysis (PHA; analyse préliminaire des risques, APR, in French) is a method for systematically identifying the hazards of a facility, carried out early in the life cycle of the project or of operations. It sweeps each system or piece of equipment to list what could go wrong, without aiming for the exhaustiveness of an FMECA or the quantitative precision of a LOPA. It is a structured first pass, often the entry point to more detailed methods for the most critical scenarios.

The method comes from US military and aerospace programmes of the 1960s, where it appears in the system safety standard MIL-STD-882. It then spread to the chemical industry, nuclear, rail and the process industries.

Unlike FMEA (dedicated standard IEC 60812) or HAZOP (IEC 61882), the PHA has no standard of its own: it is a technique described in IEC 31010 — Risk management — Risk assessment techniques. In France, it is also the first step of the hazard study required for classified installations.
Polyodos offers the PHA in two versions: PHA physical risks (general purpose, this page) and PHA hazard study (French SEVESO/ICPE regulatory variant — see the dedicated page).

2When to use a PHA

The PHA is less suited to detailed analysis of a continuous process (where the more systematic HAZOP is preferable) or to studying the reliability of a component (the domain of FMECA).

3Definitions

TermDefinition
HazardAn intrinsic property of equipment or a substance that can cause harm (e.g. “stored mechanical energy”, “toxic product”, “electrical voltage”). The hazard exists independently of any incident: it is a potential, not an event.
Undesired eventThe abnormal situation through which the hazard would materialise (e.g. “rupture of the pump casing”). It is the tipping point from potential to incident.
CauseWhat can lead to the undesired event (e.g. “prolonged cavitation”, “internal corrosion”).
ConsequenceWhat results from the undesired event if it occurs (e.g. “metal fragments ejected”, “flooding of the room”).
RiskThe combination of the severity of a consequence and its probability of occurrence.

In practice, the Hazard field is often filled in by broad category, to make sorting and statistics easier: mechanical (rupture, ejection, crushing), chemical (leak, toxicity, reaction), electrical (short circuit, electric shock), thermal, ergonomic… A list of generic hazards serves as a checklist so that nothing is forgotten.

4Before you start: model the system

Like FMECA, the PHA relies on a prior breakdown of the facility into systems and equipment — see the cross-cutting topic Facility modelling, shared by PHA, FMECA, HAZOP and bow-tie. Also gather the input documents: drawings, block diagrams, product safety data sheets, operating experience and accidents on similar facilities.

5The PHA step by step

  1. Define the scope and build the working group: facility boundaries, life phases covered (normal operation, start-up, maintenance…), participants.
  2. Break down the facility into systems or equipment (see modelling above).
  3. Identify the hazard carried by each piece of equipment (energy, substance, movement…).
  4. Describe the undesired event: the abnormal situation through which the hazard would materialise.
  5. List the causes that could lead to this event.
  6. List the potential consequences (human, environmental, material).
  7. Rate the scenario for severity and probability, before measures (see next section).
  8. List existing and planned measures, then re-rate the scenario after measures.
  9. Prioritise and decide: action plan, scenarios to examine further with a more detailed method.
The PHA lends itself well to a review by a multidisciplinary group (operations, safety, maintenance): the diversity of viewpoints is what limits blind spots, more than the sophistication of the tool.

6Rating risk in a PHA

The general principles of risk rating (matrix, scales, before/after measures) are common to all methods — see the cross-cutting topic Rating a risk. There is no standardised scale for the PHA: each organisation defines its own. The example below crosses two metrics rated from 1 to 4, the default scale in Polyodos.

Severity

LevelLabelMeaning
1NegligibleFirst aid, no lost time
2SignificantTemporary partial incapacity < 3 days
3SeriousPermanent partial incapacity, hospitalisation > 1 day
4CatastrophicDeath or permanent total incapacity

Probability (likelihood)

LevelLabelIndicative frequency
1Very unlikely< 10⁻⁴ / year
2Unlikely10⁻⁴ – 10⁻² / year
3Likely1 possible occurrence per year
4FrequentSeveral occurrences expected

Criticality matrix

Criticality results from crossing severity × probability on a configurable matrix; the level obtained is read on a 4-step scale:

LevelLabelMeaning
1AcceptableStay vigilant
2To be monitoredPlanned treatment
3Not acceptableTreatment required in the short term
4UnacceptableUrgent treatment, shutdown if necessary
The default matrix only covers severity and probability levels 1 to 4: if a scenario is rated beyond that (e.g. severity 5 on a customised scale), criticality can no longer be resolved automatically until the matrix has been extended. See the example below, where this case actually occurs.

7Existing measures and planned measures

Each scenario distinguishes existing measures (already in place, taken into account in the before-measures rating, often empty if the scenario is not yet covered) from planned measures (action plan, whose implementation justifies the after-measures rating). The same prevention / protection distinction as in FMECA applies:

TypeActs onExamples
PreventionProbabilityPeriodic vibration monitoring, visual inspection, preventive replacement of wear parts, procedure governing a hazardous operation (permit to work)
ProtectionSeverityGas detector with alarm and automatic shut-off, residual-current circuit breaker, thermal protection, retention
Work in this order of preference: eliminate the hazard, reduce it (less product, lower pressure), and only then add technical and organisational barriers.

8Example: a drinking-water treatment plant

The Polyodos demonstration data set (drinking-water treatment plant, fictitious data) covers 4 scenarios across the Pumping, Chemical treatment and Storage systems:

#System / EquipmentHazardCausesUndesired eventConsequences SPC Planned measures S'P'C'
1Pumping — Centrifugal pump P-101Mechanical Prolonged cavitation, excessive vibration, internal corrosion Rupture of the pump casing Metal fragments ejected, flooding of the pump room, production stoppage S4 P2 R3 Monthly vibration monitoring (piezoelectric sensors), replacement of mechanical seals every 2 years S3 P1 R2
2Chemical treatment — Chlorine tank CL-301Chemical Corrosion of the HDPE wall, rupture of the filling connection, overpressure during unloading Liquid chlorine leak Toxic atmosphere (chlorine gas), severe respiratory irritation, site evacuation S5 P2 R? Chlorine detector with audible alarm and automatic shut-off, unloading procedure under permit to work, annual tank inspection S4 P1 R2
3Pumping — Electric motor M-101Electrical Wiring degraded by humidity, prolonged motor overload, circuit breaker fault Short circuit with switchboard fire Fire in the electrical room, loss of power to pumping, risk of electric shock S3 P2 R2 Annual periodic inspection of the electrical installation, 30 mA residual-current breaker and motor thermal protection S2 P1 R1
4Storage — Treated-water tank CS-301Mechanical Ageing of the reinforced concrete, differential ground settlement, hydraulic overpressure Rupture of the concrete tank (structural crack) Massive overflow (500 m³), flooding of the downstream area, groundwater contamination S4 P1 R2 Quarterly visual inspection (cracks, deformation), geotechnical soil survey every 10 years S3 P1 R2
PHA worksheet — drinking-water treatment plant, fictitious data (before / after measures; S = severity, P = probability, C = criticality)
Line 2: the chlorine tank is rated severity 5, outside the default scale (1 to 4): its before-measures criticality therefore cannot be read on the standard matrix until the matrix is extended to that level. The case is deliberate: it illustrates the pitfall described above (customised scale not carried over to the matrix).

Reading the result and action plan

Sorted by before-measures criticality, the worksheet directly gives the order of treatment:

PriorityScenarioBefore measuresAfter measuresDecision
1Liquid chlorine leak (CL-301)S5 × P2, outside the matrixS4 × P1 → R2Extend the matrix to severity 5, then examine the scenario further with a bow-tie
2Pump casing rupture (P-101)S4 × P2 → R3S3 × P1 → R2Measures to be implemented in the short term; vibration monitoring to be added to the maintenance plan
3Concrete tank rupture (CS-301)S4 × P1 → R2S3 × P1 → R2Residual risk to be monitored: severity remains high, and only a protection measure (retention, downstream warning) could reduce it
4Switchboard fire (M-101)S3 × P2 → R2S2 × P1 → R1Measures planned, residual risk acceptable

Of 4 scenarios, 2 must be treated as a priority and 1 warrants a detailed analysis. This example is handled in Polyodos, from worksheet to Word report. See the Industrial risks demo or try Polyodos free for 30 days.

9Common mistakes

MistakeWhy it is a problem
Confusing hazard and undesired eventThe hazard is an intrinsic property (“high pressure”), the undesired event an abnormal situation (“tank rupture”): mixing them makes the causes inconsistent.
Rating only after measuresWithout a before-measures rating, it is impossible to judge how effective the barriers really are or to prioritise the most critical scenarios.
Extending a scale without extending the matrixAdding a customised severity level (e.g. 5) without updating the criticality matrix leaves scenarios with no computable risk level — see the example above.
Forgetting transient phasesStart-up, shutdown, maintenance and unloading account for a large share of accidents: a PHA limited to normal operation misses them.
Aiming for exhaustiveness at the expense of perspectiveThe PHA loses its value if it turns into a disguised FMECA: a broad overview is better, with critical scenarios examined in depth afterwards using HAZOP or FMECA.

10Further reading

Learn: the online courses Industrial risks and Technical and industrial risk analysis on aurorisk.com.

Practise: the Industrial risks module user guide in Polyodos.