1What is a bow-tie?
The bow-tie places the top event (in French practice, the événement redouté central, ERC) at the centre of a diagram shaped like a bow tie:
- on the left, the causes (threats) that can lead to it, each intercepted by prevention barriers;
- on the right, the consequences that can result from it, each limited by mitigation barriers.
The left-hand side follows the logic of a fault tree, the right-hand side that of an event tree. The bow-tie brings them together around a single tipping point and puts the emphasis on the barriers: which ones exist, where they act, and what happens if they fail.
The method spread through the oil and chemical industries from the 1990s onwards. In France, it is widely used in the études de dangers (the regulatory hazard studies required for classified installations), where barriers are called mesures de maîtrise des risques (MMR, risk control measures), to represent each major accident scenario and justify its probability.
Its strength is communication: a bow-tie is far easier to read and present in a meeting than a HAZOP worksheet or a fault tree, while remaining rigorous.
2Elements of the diagram
| Element | Role | Example |
|---|---|---|
| Top event | The moment control is lost: before it, the event can still be avoided; after it, only its effects can be limited. | Loss of containment of a storage tank |
| Cause (threat or initiating event) | What can lead to the top event. | Overfilling, corrosion |
| Prevention barrier | Stops a cause from leading to the top event. | High-level alarm, inspection |
| Consequence | What can result from the top event: a hazardous phenomenon and its effects. | Pool fire, pollution |
| Mitigation barrier | Limits the top event or its effects once it has occurred. | Retention bund, fire extinguishing |
| Escalation factor | Something that can make a barrier ineffective (missed maintenance, bypass). | Alarm inhibited during maintenance work |
3The method, step by step
- Choose the hazard and the top event: the tipping point of the scenario, for example “loss of containment”.
- List the causes on the left-hand side, often taken from a PHA, a HAZOP or a hazard study.
- List the consequences on the right-hand side: hazardous phenomena and their effects on people, the environment and assets.
- Place the prevention barriers on each path between a cause and the top event.
- Place the mitigation barriers on each path between the top event and a consequence.
- Qualify each barrier: effectiveness, response time, independence, testing and maintenance; record the factors that can degrade it.
- (quantified version) Quantify: cause frequencies, barrier failure probabilities, then the frequency of the top event and of each consequence.
4Example: loss of containment of a storage tank
An atmospheric storage tank of flammable liquid, located inside a retention bund, is filled by unloading road tankers. Top event: loss of containment of the tank. Fictitious values.
Left-hand side: causes and prevention barriers
| Cause | Frequency | Prevention barriers (probability of failure) | Frequency towards the top event |
|---|---|---|---|
| Overfilling during unloading | 0.1 /yr | High-level alarm and operator shutdown (0.1); high-high level detection, on a separate sensor, closing the inlet valve (0.01) | 0.1 × 0.1 × 0.01 = 10-4 /yr |
| Corrosion of the shell or bottom | 10-3 /yr | Inspection plan with thickness measurements (0.1) | 10-3 × 0.1 = 10-4 /yr |
| Vehicle impact on a tank pipe | 10-2 /yr | Mechanical protection by crash barriers (0.1) | 10-2 × 0.1 = 10-3 /yr |
| Top event frequency (OR gate, sum of the paths) | 1.2 × 10-3 /yr | ||
Right-hand side: consequences and mitigation barriers
| Consequence | Barriers and probabilities | Calculation | Frequency |
|---|---|---|---|
| Soil and water pollution from a release outside the bund | Leak-tight, properly sized retention bund (failure 0.01) | 1.2 × 10-3 × 0.01 | 1.2 × 10-5 /yr |
| Uncontrolled pool fire in the bund | Probability of ignition (0.1); fire detection and foam extinguishing (failure 0.1) | 1.2 × 10-3 × 0.1 × 0.1 | 1.2 × 10-5 /yr |
Reading: vehicle impact alone accounts for more than 80% of the top event frequency (10-3 out of 1.2 × 10-3). This path, protected by a single barrier, is where strengthening is most useful, rather than overfilling, which is already covered by two barriers. Summing the paths is a valid approximation because the frequencies are low and the causes independent.
In Polyodos, the bow-tie editor of the Industrial risks module offers a simple mode (causes, barriers, consequences) and an advanced mode (logic gates, probabilities, minimal cut sets); a diagram can be created from a scenario of the PHA, the hazard study, the HAZOP or the fault tree. See the Industrial risks demo or try Polyodos free for 30 days.
5Common mistakes
| Mistake | Why it is a problem |
|---|---|
| Choosing a top event too far upstream or downstream | A top event that is already a consequence (“fire”) or still a cause (“valve stuck”) unbalances the diagram: half of the barriers end up on the wrong side. |
| Counting the same barrier twice | A barrier shared by several paths must not be counted as if each path had its own protection: double counting overstates risk control. |
| Mixing up prevention and mitigation | A prevention barrier acts before the top event, a mitigation barrier acts after it. Placing them on the wrong side distorts both the reading and the calculation. |
| Mistaking an intention for a barrier | “Staff training” or “compliance with procedures” are not barriers until you can say what is triggered, when, and how effectively. |
| Reading a calculation into a qualitative version | A bow-tie without probabilities describes the scenario; it says nothing about its frequency. To conclude on a risk level, you need the quantified version or a LOPA. |