← Polyodos · Methods wiki · Industrial and technical risks
Method

🎀 Bow-tie

The most readable representation of a risk scenario: causes and prevention barriers on the left, consequences and mitigation barriers on the right, on either side of the central top event.

1What is a bow-tie?

The bow-tie places the top event (in French practice, the événement redouté central, ERC) at the centre of a diagram shaped like a bow tie:

The left-hand side follows the logic of a fault tree, the right-hand side that of an event tree. The bow-tie brings them together around a single tipping point and puts the emphasis on the barriers: which ones exist, where they act, and what happens if they fail.

The method spread through the oil and chemical industries from the 1990s onwards. In France, it is widely used in the études de dangers (the regulatory hazard studies required for classified installations), where barriers are called mesures de maîtrise des risques (MMR, risk control measures), to represent each major accident scenario and justify its probability.

Its strength is communication: a bow-tie is far easier to read and present in a meeting than a HAZOP worksheet or a fault tree, while remaining rigorous.

Two levels of detail are possible: a qualitative version (causes, barriers, consequences) to share an understanding of the scenario, and a quantified version (cause frequencies, barrier failure probabilities, logic gates) to estimate the frequency of each consequence.

2Elements of the diagram

ElementRoleExample
Top eventThe moment control is lost: before it, the event can still be avoided; after it, only its effects can be limited.Loss of containment of a storage tank
Cause (threat or initiating event)What can lead to the top event.Overfilling, corrosion
Prevention barrierStops a cause from leading to the top event.High-level alarm, inspection
ConsequenceWhat can result from the top event: a hazardous phenomenon and its effects.Pool fire, pollution
Mitigation barrierLimits the top event or its effects once it has occurred.Retention bund, fire extinguishing
Escalation factorSomething that can make a barrier ineffective (missed maintenance, bypass).Alarm inhibited during maintenance work

3The method, step by step

  1. Choose the hazard and the top event: the tipping point of the scenario, for example “loss of containment”.
  2. List the causes on the left-hand side, often taken from a PHA, a HAZOP or a hazard study.
  3. List the consequences on the right-hand side: hazardous phenomena and their effects on people, the environment and assets.
  4. Place the prevention barriers on each path between a cause and the top event.
  5. Place the mitigation barriers on each path between the top event and a consequence.
  6. Qualify each barrier: effectiveness, response time, independence, testing and maintenance; record the factors that can degrade it.
  7. (quantified version) Quantify: cause frequencies, barrier failure probabilities, then the frequency of the top event and of each consequence.
A barrier counts only if it is genuinely independent and effective for this specific scenario. Copying the same list of generic barriers onto every top event of a study is the sign of a superficial analysis.

4Example: loss of containment of a storage tank

An atmospheric storage tank of flammable liquid, located inside a retention bund, is filled by unloading road tankers. Top event: loss of containment of the tank. Fictitious values.

Left-hand side: causes and prevention barriers

CauseFrequencyPrevention barriers (probability of failure)Frequency towards the top event
Overfilling during unloading0.1 /yrHigh-level alarm and operator shutdown (0.1); high-high level detection, on a separate sensor, closing the inlet valve (0.01)0.1 × 0.1 × 0.01 = 10-4 /yr
Corrosion of the shell or bottom10-3 /yrInspection plan with thickness measurements (0.1)10-3 × 0.1 = 10-4 /yr
Vehicle impact on a tank pipe10-2 /yrMechanical protection by crash barriers (0.1)10-2 × 0.1 = 10-3 /yr
Top event frequency (OR gate, sum of the paths)1.2 × 10-3 /yr

Right-hand side: consequences and mitigation barriers

ConsequenceBarriers and probabilitiesCalculationFrequency
Soil and water pollution from a release outside the bundLeak-tight, properly sized retention bund (failure 0.01)1.2 × 10-3 × 0.011.2 × 10-5 /yr
Uncontrolled pool fire in the bundProbability of ignition (0.1); fire detection and foam extinguishing (failure 0.1)1.2 × 10-3 × 0.1 × 0.11.2 × 10-5 /yr

Reading: vehicle impact alone accounts for more than 80% of the top event frequency (10-3 out of 1.2 × 10-3). This path, protected by a single barrier, is where strengthening is most useful, rather than overfilling, which is already covered by two barriers. Summing the paths is a valid approximation because the frequencies are low and the causes independent.

In Polyodos, the bow-tie editor of the Industrial risks module offers a simple mode (causes, barriers, consequences) and an advanced mode (logic gates, probabilities, minimal cut sets); a diagram can be created from a scenario of the PHA, the hazard study, the HAZOP or the fault tree. See the Industrial risks demo or try Polyodos free for 30 days.

5Common mistakes

MistakeWhy it is a problem
Choosing a top event too far upstream or downstreamA top event that is already a consequence (“fire”) or still a cause (“valve stuck”) unbalances the diagram: half of the barriers end up on the wrong side.
Counting the same barrier twiceA barrier shared by several paths must not be counted as if each path had its own protection: double counting overstates risk control.
Mixing up prevention and mitigationA prevention barrier acts before the top event, a mitigation barrier acts after it. Placing them on the wrong side distorts both the reading and the calculation.
Mistaking an intention for a barrier“Staff training” or “compliance with procedures” are not barriers until you can say what is triggered, when, and how effectively.
Reading a calculation into a qualitative versionA bow-tie without probabilities describes the scenario; it says nothing about its frequency. To conclude on a risk level, you need the quantified version or a LOPA.

6Further reading

Learn: the online courses Industrial risks and Hazard study (in French) on aurorisk.com.

Practise: the user guide for the Industrial risks module of Polyodos.