Regulatory method

🧪 PHA — Hazard study (SEVESO)

The regulatory variant of the PHA for SEVESO sites and permitted classified installations in France: hazardous phenomena, intensity of effects, severity, probability classes A to E and the MMR grid.

1What is a hazard study?

The hazard study (étude de dangers, EDD) is the centrepiece of the permit application for French ICPE (installations classées pour la protection de l’environnement, classified installations for environmental protection) subject to authorisation, and in particular for lower-tier and upper-tier SEVESO establishments. In it, the operator sets out the hazards the facility may present in the event of an accident, the possible major accidents and their effects, and the measures taken to reduce their probability and effects.

The approach follows the structure of the PHA (hazard → event → consequence) but with vocabulary and requirements specific to French regulations: initiating event, critical event (événement redouté central, ERC), hazardous phenomenon, risk control measures (mesures de maîtrise des risques, MMR), and an assessment against four criteria set by ministerial order: probability, kinetics, intensity and severity (often abbreviated PCIG or PIGC).

The PHA is the first step of the hazard study: it sweeps the facility to identify hazardous phenomena. The potential major accidents it reveals are then analysed in detail, often as a bow-tie, and placed in the MMR grid.

2Reference texts

TextWhat it provides
Directive 2012/18/EU (“SEVESO III”)European framework for the prevention of major accidents involving dangerous substances; lower-tier / upper-tier classification.
Code de l’environnement (French Environment Code)The classified installations regime and the obligation to include a hazard study in the permit application.
Arrêté du 29 septembre 2005 (ministerial order of 29 September 2005)Assessment and consideration of the probability of occurrence, kinetics, intensity of effects and severity of consequences of potential accidents: effect thresholds, probability classes A to E, five-level severity scale.
Circulaire du 10 mai 2010 (circular of 10 May 2010)Summarises the methodological rules applicable to hazard studies and to the assessment of risk reduction at source; contains the MMR grid used to appraise major accidents.

The INERIS guides and the ARIA accident database (BARPI) complement these texts for methodology and accident history.

3Vocabulary: from initiating event to hazardous phenomenon

TermDefinitionExample
Initiating eventThe failure, error or external aggression at the origin of the accident sequence.Rupture of an unloading hose
Critical event (ERC)The loss of containment or loss of control at the centre of the bow-tie.Ethanol spill on the unloading area
Hazardous phenomenonThe release of energy or substance producing effects (thermal, overpressure, toxic).Pool fire
Major accidentThe hazardous phenomenon once it reaches targets (people, property, environment) with serious consequences.People exposed on the public road
Risk control measure (MMR)A technical or organisational barrier that reduces the probability or effects of a major accident, provided it is effective, has a suitable response time, and is tested and maintained.Emergency shutdown of unloading on leak detection
Distinguish a passive MMR (works without any action, e.g. retention bund, firewall) from an active MMR (requires detection, decision and action, e.g. automatic extinguishing): the expected reliability and the justification are not the same.

4The hazard study step by step

  1. Describe the facility and its surroundings: processes, products, quantities, and nearby targets (homes, establishments open to the public, traffic routes).
  2. Identify the hazard potentials (dangerous products, stored energy…) and study their reduction at source: smaller quantities, substitution, greater distance.
  3. Use accident history: accidents on the site and on similar facilities.
  4. Carry out the PHA: for each system, initiating events, critical events, hazardous phenomena and existing measures.
  5. Assess the intensity and kinetics of each hazardous phenomenon: effect distances at the regulatory thresholds.
  6. Rate severity and probability of each potential major accident, with the detailed analysis of the scenarios that justify it (bow-tie, MMR assessment).
  7. Place the accidents in the MMR grid and justify the risk reduction approach; add measures where necessary.

5Intensity, severity, probability, kinetics

Intensity: effect thresholds

Intensity is measured by the distances at which a phenomenon reaches the thresholds set by the arrêté du 29 septembre 2005:

ThresholdThermal effectsOverpressure effects
SEI — irreversible effects3 kW/m²50 mbar
SEL — first lethal effects5 kW/m²140 mbar
SELS — significant lethal effects8 kW/m²200 mbar

For toxic effects, the thresholds are specific to each substance and to the exposure duration. The 20 mbar threshold corresponds to indirect effects from broken windows.

Severity: five levels

Severity depends on the number of people exposed outside the establishment in each effect zone. The highest level reached in any of the three zones is retained:

LevelSELS zoneSEL zoneSEI zone
Disastrous (Désastreux)More than 10 peopleMore than 100 peopleMore than 1,000 people
Catastrophic (Catastrophique)Fewer than 10 peopleBetween 10 and 100Between 100 and 1,000
Major (Important)At most 1 personBetween 1 and 10Between 10 and 100
Serious (Sérieux)NobodyAt most 1 personFewer than 10 people
Moderate (Modéré)No lethal effect zone outside the establishmentLess than one person

Probability: classes A to E

The probability of each accident falls into one of the five classes of the order. It may be assessed qualitatively, semi-quantitatively or quantitatively:

ClassLabelQualitative benchmarkIndicative frequency
ACommon eventHas occurred on the site and/or may occur several times during the facility’s lifetime> 10⁻² / year
BProbable eventHas occurred and/or may occur during the facility’s lifetime10⁻³ to 10⁻² / year
CImprobable eventA similar event has already occurred in the industry sector, with no guarantee that the corrections made since significantly reduce its probability10⁻⁴ to 10⁻³ / year
DVery improbable eventHas already occurred in this industry sector, but has been subject to corrective measures that significantly reduce its probability10⁻⁵ to 10⁻⁴ / year
EPossible but extremely unlikelyNot impossible given current knowledge, but never encountered worldwide over a very large number of installation-years< 10⁻⁵ / year

Kinetics

Kinetics is slow if it leaves time to implement measures protecting people (warning, evacuation) before they are reached, and fast otherwise. The measures selected must have a response time suited to the kinetics of the phenomenon they are meant to control.

6The MMR grid

The circulaire du 10 mai 2010 provides a grid that crosses the severity and probability class of each potential major accident:

Severity \ ProbabilityEDCBA
DisastrousPartial NON (new) / MMR rank 2 (existing)NON rank 1NON rank 2NON rank 3NON rank 4
CatastrophicMMR rank 1MMR rank 2NON rank 1NON rank 2NON rank 3
MajorMMR rank 1MMR rank 1MMR rank 2NON rank 1NON rank 2
Serious——MMR rank 1MMR rank 2NON rank 1
Moderate————MMR rank 1

The circular adds an accumulation rule: beyond five accidents in “MMR rank 2” cells, the whole is appraised as a “NON rank 1” cell.

The grid above is a reading aid. Only the version published in the Bulletin officiel is authoritative, particularly for its footnotes (new or existing establishments, extensions, special cases such as pyrotechnics).

7Example: an ethanol storage facility

A fictitious depot stores ethanol in a 500 m³ tank inside a retention bund, filled by road tanker from an unloading area. A secondary road runs along the site 30 m from the bund; a neighbouring company is 60 m from the unloading area. Three potential major accidents emerge from the PHA:

#Initiating event → critical eventHazardous phenomenonSELS / SEL / SEI distancesPeople exposed off siteSeverityMMRs creditedProb.Grid cell
1Tank bottom corrosion → leak into the bundBund fire25 / 35 / 50 mSEI: 6 (road)SeriousRetention bund, low-level detection, periodic tank inspectionCMMR rank 1
2Unloading hose rupture → spill on the areaPool fire45 / 65 / 90 mSEL: 3 · SEI: 25 (neighbouring company)MajorEmergency shutdown of unloading on leak detection, unloading area drained to a remote retentionDMMR rank 1
3Ignition of the vapour space → tank explosionTank explosion (overpressure effects)20 / 30 / 70 mSEL: 2 · SEI: 30 (road, neighbouring company)MajorEarthing and equipotential bonding, sized vents, inertingEMMR rank 1
Potential major accidents of an ethanol storage facility — fictitious data, effect distances not derived from actual modelling

The severity of accident 2 is read in the most penalising zone: 3 people in the SEL zone and 25 in the SEI zone both place it at “Major”. Its class D relies entirely on the emergency shutdown of unloading: without this MMR, the probability would be class B and the accident would fall into NON rank 1. That is why the study must demonstrate the effectiveness, response time and long-term maintenance of this barrier.

No accident is in a NON cell and none is in MMR rank 2: the risk reduction approach must still continue, with priority on unloading. This example is handled in Polyodos, from worksheet to Word report. See the Industrial risks demo or try Polyodos free for 30 days.

8Common mistakes

MistakeWhy it is a problem
Customising the regulatory scalesProbability classes A to E, severity levels and the MMR grid are set by the texts: changing them strips the file of any basis for comparison and exposes it to rejection by the inspectorate.
Confusing critical event and hazardous phenomenonThe critical event is the loss of containment or control; the hazardous phenomenon is what happens next (fire, explosion). One feeds the other; they are not interchangeable.
Counting people exposed on siteRegulatory severity is based on people exposed outside the establishment; site personnel fall under other regulations.
Crediting a barrier without justifying itA measure only lowers the probability class if its effectiveness, response time, testing and maintenance are demonstrated. A single barrier, even a reliable one, is rarely enough: several independent MMRs are generally expected.
Forgetting reduction at sourceBefore adding barriers, the study must show that efforts were made to reduce the hazard potential itself (quantities, operating conditions, layout).