1What is a hazard study?
The hazard study (étude de dangers, EDD) is the centrepiece of the permit application for French ICPE (installations classées pour la protection de l’environnement, classified installations for environmental protection) subject to authorisation, and in particular for lower-tier and upper-tier SEVESO establishments. In it, the operator sets out the hazards the facility may present in the event of an accident, the possible major accidents and their effects, and the measures taken to reduce their probability and effects.
The approach follows the structure of the PHA (hazard → event → consequence) but with vocabulary and requirements specific to French regulations: initiating event, critical event (événement redouté central, ERC), hazardous phenomenon, risk control measures (mesures de maîtrise des risques, MMR), and an assessment against four criteria set by ministerial order: probability, kinetics, intensity and severity (often abbreviated PCIG or PIGC).
2Reference texts
| Text | What it provides |
|---|---|
| Directive 2012/18/EU (“SEVESO III”) | European framework for the prevention of major accidents involving dangerous substances; lower-tier / upper-tier classification. |
| Code de l’environnement (French Environment Code) | The classified installations regime and the obligation to include a hazard study in the permit application. |
| Arrêté du 29 septembre 2005 (ministerial order of 29 September 2005) | Assessment and consideration of the probability of occurrence, kinetics, intensity of effects and severity of consequences of potential accidents: effect thresholds, probability classes A to E, five-level severity scale. |
| Circulaire du 10 mai 2010 (circular of 10 May 2010) | Summarises the methodological rules applicable to hazard studies and to the assessment of risk reduction at source; contains the MMR grid used to appraise major accidents. |
The INERIS guides and the ARIA accident database (BARPI) complement these texts for methodology and accident history.
3Vocabulary: from initiating event to hazardous phenomenon
| Term | Definition | Example |
|---|---|---|
| Initiating event | The failure, error or external aggression at the origin of the accident sequence. | Rupture of an unloading hose |
| Critical event (ERC) | The loss of containment or loss of control at the centre of the bow-tie. | Ethanol spill on the unloading area |
| Hazardous phenomenon | The release of energy or substance producing effects (thermal, overpressure, toxic). | Pool fire |
| Major accident | The hazardous phenomenon once it reaches targets (people, property, environment) with serious consequences. | People exposed on the public road |
| Risk control measure (MMR) | A technical or organisational barrier that reduces the probability or effects of a major accident, provided it is effective, has a suitable response time, and is tested and maintained. | Emergency shutdown of unloading on leak detection |
4The hazard study step by step
- Describe the facility and its surroundings: processes, products, quantities, and nearby targets (homes, establishments open to the public, traffic routes).
- Identify the hazard potentials (dangerous products, stored energy…) and study their reduction at source: smaller quantities, substitution, greater distance.
- Use accident history: accidents on the site and on similar facilities.
- Carry out the PHA: for each system, initiating events, critical events, hazardous phenomena and existing measures.
- Assess the intensity and kinetics of each hazardous phenomenon: effect distances at the regulatory thresholds.
- Rate severity and probability of each potential major accident, with the detailed analysis of the scenarios that justify it (bow-tie, MMR assessment).
- Place the accidents in the MMR grid and justify the risk reduction approach; add measures where necessary.
5Intensity, severity, probability, kinetics
Intensity: effect thresholds
Intensity is measured by the distances at which a phenomenon reaches the thresholds set by the arrêté du 29 septembre 2005:
| Threshold | Thermal effects | Overpressure effects |
|---|---|---|
| SEI — irreversible effects | 3 kW/m² | 50 mbar |
| SEL — first lethal effects | 5 kW/m² | 140 mbar |
| SELS — significant lethal effects | 8 kW/m² | 200 mbar |
For toxic effects, the thresholds are specific to each substance and to the exposure duration. The 20 mbar threshold corresponds to indirect effects from broken windows.
Severity: five levels
Severity depends on the number of people exposed outside the establishment in each effect zone. The highest level reached in any of the three zones is retained:
| Level | SELS zone | SEL zone | SEI zone |
|---|---|---|---|
| Disastrous (Désastreux) | More than 10 people | More than 100 people | More than 1,000 people |
| Catastrophic (Catastrophique) | Fewer than 10 people | Between 10 and 100 | Between 100 and 1,000 |
| Major (Important) | At most 1 person | Between 1 and 10 | Between 10 and 100 |
| Serious (Sérieux) | Nobody | At most 1 person | Fewer than 10 people |
| Moderate (Modéré) | No lethal effect zone outside the establishment | Less than one person | |
Probability: classes A to E
The probability of each accident falls into one of the five classes of the order. It may be assessed qualitatively, semi-quantitatively or quantitatively:
| Class | Label | Qualitative benchmark | Indicative frequency |
|---|---|---|---|
| A | Common event | Has occurred on the site and/or may occur several times during the facility’s lifetime | > 10⁻² / year |
| B | Probable event | Has occurred and/or may occur during the facility’s lifetime | 10⁻³ to 10⁻² / year |
| C | Improbable event | A similar event has already occurred in the industry sector, with no guarantee that the corrections made since significantly reduce its probability | 10⁻⁴ to 10⁻³ / year |
| D | Very improbable event | Has already occurred in this industry sector, but has been subject to corrective measures that significantly reduce its probability | 10⁻⁵ to 10⁻⁴ / year |
| E | Possible but extremely unlikely | Not impossible given current knowledge, but never encountered worldwide over a very large number of installation-years | < 10⁻⁵ / year |
Kinetics
Kinetics is slow if it leaves time to implement measures protecting people (warning, evacuation) before they are reached, and fast otherwise. The measures selected must have a response time suited to the kinetics of the phenomenon they are meant to control.
6The MMR grid
The circulaire du 10 mai 2010 provides a grid that crosses the severity and probability class of each potential major accident:
| Severity \ Probability | E | D | C | B | A |
|---|---|---|---|---|---|
| Disastrous | Partial NON (new) / MMR rank 2 (existing) | NON rank 1 | NON rank 2 | NON rank 3 | NON rank 4 |
| Catastrophic | MMR rank 1 | MMR rank 2 | NON rank 1 | NON rank 2 | NON rank 3 |
| Major | MMR rank 1 | MMR rank 1 | MMR rank 2 | NON rank 1 | NON rank 2 |
| Serious | — | — | MMR rank 1 | MMR rank 2 | NON rank 1 |
| Moderate | — | — | — | — | MMR rank 1 |
- NO (“no”): risk presumed too high; the rank indicates how difficult it is to return to an acceptable zone.
- MMR: intermediate zone, where a continuous improvement approach is expected to reduce the risk as far as possible under economically acceptable conditions.
- —: lower risk.
The circular adds an accumulation rule: beyond five accidents in “MMR rank 2” cells, the whole is appraised as a “NON rank 1” cell.
7Example: an ethanol storage facility
A fictitious depot stores ethanol in a 500 m³ tank inside a retention bund, filled by road tanker from an unloading area. A secondary road runs along the site 30 m from the bund; a neighbouring company is 60 m from the unloading area. Three potential major accidents emerge from the PHA:
| # | Initiating event → critical event | Hazardous phenomenon | SELS / SEL / SEI distances | People exposed off site | Severity | MMRs credited | Prob. | Grid cell |
|---|---|---|---|---|---|---|---|---|
| 1 | Tank bottom corrosion → leak into the bund | Bund fire | 25 / 35 / 50 m | SEI: 6 (road) | Serious | Retention bund, low-level detection, periodic tank inspection | C | MMR rank 1 |
| 2 | Unloading hose rupture → spill on the area | Pool fire | 45 / 65 / 90 m | SEL: 3 · SEI: 25 (neighbouring company) | Major | Emergency shutdown of unloading on leak detection, unloading area drained to a remote retention | D | MMR rank 1 |
| 3 | Ignition of the vapour space → tank explosion | Tank explosion (overpressure effects) | 20 / 30 / 70 m | SEL: 2 · SEI: 30 (road, neighbouring company) | Major | Earthing and equipotential bonding, sized vents, inerting | E | MMR rank 1 |
The severity of accident 2 is read in the most penalising zone: 3 people in the SEL zone and 25 in the SEI zone both place it at “Major”. Its class D relies entirely on the emergency shutdown of unloading: without this MMR, the probability would be class B and the accident would fall into NON rank 1. That is why the study must demonstrate the effectiveness, response time and long-term maintenance of this barrier.
No accident is in a NON cell and none is in MMR rank 2: the risk reduction approach must still continue, with priority on unloading. This example is handled in Polyodos, from worksheet to Word report. See the Industrial risks demo or try Polyodos free for 30 days.
8Common mistakes
| Mistake | Why it is a problem |
|---|---|
| Customising the regulatory scales | Probability classes A to E, severity levels and the MMR grid are set by the texts: changing them strips the file of any basis for comparison and exposes it to rejection by the inspectorate. |
| Confusing critical event and hazardous phenomenon | The critical event is the loss of containment or control; the hazardous phenomenon is what happens next (fire, explosion). One feeds the other; they are not interchangeable. |
| Counting people exposed on site | Regulatory severity is based on people exposed outside the establishment; site personnel fall under other regulations. |
| Crediting a barrier without justifying it | A measure only lowers the probability class if its effectiveness, response time, testing and maintenance are demonstrated. A single barrier, even a reliable one, is rarely enough: several independent MMRs are generally expected. |
| Forgetting reduction at source | Before adding barriers, the study must show that efforts were made to reduce the hazard potential itself (quantities, operating conditions, layout). |