๐Ÿ“ Rating a risk

The principles shared by all risk-analysis methods: severity and likelihood scales, the risk matrix, inherent and residual risk. Each method then adds its own metrics.

1General principle

Rating a risk means placing it on two axes:

Combining the two gives a risk level, which is used to prioritise: deal first with what is both severe and likely, accept what is low, and monitor what lies in between.

Rating is not meant to produce an exact figure, but to compare risks with each other using rules shared by the whole team. Two people rating the same scenario should reach the same result.

2Severity and likelihood scales

A scale usually has 3 to 5 levels. Four levels is a common choice: an even number avoids a "medium" level where everything nobody dares to decide ends up. Each level must be described by observable criteria, not by an adjective alone.

LevelSeverity (example)Likelihood (example)
1Minor: inconvenience with no lasting impact, a few hours of downtimeUnlikely: never seen in the sector, requires a combination of circumstances
2Significant: degraded service, controlled costLikely: already observed in the sector
3Serious: shutdown of a major activity, reputational damage, injuryVery likely: has already happened in the organisation
4Critical: endangers the organisation or peopleAlmost certain: happens regularly

Two families of scales coexist:

Severity is often broken down into several criteria (human, financial, environmental, reputational, legal). The level of the most affected criterion is then used.

3The risk matrix

The matrix combines the two scales and assigns a risk level to each cell. Each level corresponds to a decision. Example of a 4ร—4 matrix with three levels:

Likelihood โ†“ / Severity โ†’S1 MinorS2 SignificantS3 SeriousS4 Critical
L4 Almost certainModerateHighHighHigh
L3 Very likelyLowModerateHighHigh
L2 LikelyLowModerateModerateHigh
L1 UnlikelyLowLowModerateModerate
LevelAssociated decision
LowRisk acceptable as it stands, reviewed periodically
ModerateRisk tolerated under monitoring, treatment planned if the cost is reasonable
HighUnacceptable risk: priority treatment, management decision

The matrix is not necessarily symmetrical: many organisations give more weight to severity, so that a critical scenario is never classed as "low", even if it is rare. The thresholds express the organisation's risk appetite: they are set before rating, and approved by management.

4Inherent risk and residual risk

Risks are usually rated twice:

The difference between the two measures the expected effect of the measures. A prevention measure lowers likelihood; a protection or mitigation measure lowers severity. Residual risk is the risk that management must formally accept.

State in writing what "inherent" includes: no measures at all, or existing measures. Both conventions exist depending on the method, and mixing them within the same study makes the differences impossible to compare.

5Rating in ISO 31000

ISO 31000 (risk management guidelines) defines risk as the effect of uncertainty on objectives. Its process runs as follows:

  1. Establish the context and the risk criteria: this is where scales and thresholds are set.
  2. Assess the risk: identify it, analyse it (severity, likelihood, level), then evaluate it by comparing it with the criteria.
  3. Treat the risk: reduce, avoid, transfer or accept.
  4. Monitor and review, communicating throughout the process.

ISO 31000 prescribes neither a scale nor a matrix: it requires criteria to be defined in advance and consistent with the organisation's objectives. The severity ร— likelihood matrix is one of the techniques described in the companion standard IEC 31010.

6Example: three rated risks

Fictitious example in an industrial SME, using the matrix above:

RiskInherentMeasures decidedResidual
Ransomware paralysing productionS4 ร— L3 HighTested offline backups (severity), multi-factor authentication and segmentation (likelihood)S3 ร— L2 Moderate
Operator falling from a walkwayS3 ร— L3 HighGuardrails and periodic inspectionS3 ร— L1 Moderate
Failure of an office workstationS1 ร— L3 LowNone: risk acceptedS1 ร— L3 Low

Ransomware remains "moderate" after treatment: it is up to management to decide whether this level is acceptable or whether further measures are needed.

In Polyodos, each analysis module (EBIOS RM, industrial risks, occupational risks) has its own scales and risk matrix and, depending on the method, distinguishes the rating before and after measures. See the demo or try Polyodos free for 30 days.

7Method-specific metrics

MethodRating
EBIOS RMSeverity of feared events and likelihood of scenarios, usually on four-level scales
PHASeverity ร— probability, before and after measures
Hazard study (safety report)Severity and probability according to regulatory classes, positioned on the criticality grid
FMEASeverity ร— occurrence ร— detection, whose product gives a priority number
LOPAInitiating event frequency multiplied by the probability of failure on demand of each barrier, compared with a target frequency

8Common mistakes

MistakeWhy it is a problem
Levels without criteria"Serious" or "likely" without a definition lead to different ratings depending on the person: comparisons lose their meaning.
Setting thresholds after ratingThe matrix then gets adjusted to obtain the desired result. Criteria are decided beforehand and approved by management.
Rating everything in the middleA rating that avoids the extremes no longer prioritises anything. An even-numbered scale limits this bias.
Multiplying levels as if they were numbersOn a qualitative scale, level 4 is not "twice" level 2. An S ร— L product can serve as a guide, but the matrix remains the reference.
Forgetting residual riskWithout a rating after measures, you know neither whether the measures are sufficient nor what management is accepting.