← Polyodos · Methods wiki · Industrial and technical risks
Method

🔍 HAZOP

HAZard and OPerability study: the systematic analysis of process deviations using guide words, born in the chemical industry and standardised by IEC 61882.

1What is HAZOP?

HAZOP (HAZard and OPerability study) analyses a process node by node. For each node, it systematically applies guide words (NO, MORE, LESS, REVERSE, OTHER THAN…) to process parameters (flow, pressure, temperature, level…) to generate deviations from the design intent, then analyses their causes, consequences and existing safeguards.

Its strength is systematic coverage: combining guide word × parameter forces the team to examine drifts that free discussion might never raise (for example NO FLOW on a feed line). As its name says, it covers both hazards and operability problems (shutdowns, quality, operating difficulties).

The method was developed in the 1960s in the United Kingdom by the chemical company ICI, then spread widely across the petrochemical industry. It is standardised by IEC 61882 — Hazard and operability studies (HAZOP studies) — Application guide (second edition, 2016).

2When to use HAZOP

HAZOP suits continuous fluid processes (chemicals, petrochemicals, pharmaceuticals, water treatment, energy). It is time-consuming: several weeks of sessions for a complex unit. For a first screening, a PHA is faster; to quantify the critical scenarios it identifies, HAZOP is often followed by a LOPA.

3Nodes, parameters and guide words

A node is a homogeneous section of the facility with a defined design intent (for example “feed line between pump P-101 and reactor R-201”). The parameters describe that intent: flow, pressure, temperature, level, composition, viscosity, time, sequence…

The basic guide words described in IEC 61882:

Guide wordMeaningExample deviation
NO / NOTComplete negation of the intentNo flow
MOREQuantitative increasePressure too high
LESSQuantitative decreaseTemperature too low
AS WELL ASQualitative additionWater present in the product
PART OFQualitative decreaseComponent missing from a mixture
REVERSELogical opposite of the intentReverse flow
OTHER THANComplete substitutionWrong product transferred

For time and sequence deviations, add BEFORE / AFTER and EARLY / LATE, which are particularly useful for batch processes.

4HAZOP step by step

IEC 61882 divides the study into four phases: definition (scope, objectives, team), preparation (documents, node breakdown, schedule), examination (the sessions) and documentation and follow-up. The examination itself follows the loop below:

  1. Build the team: an independent facilitator (chair), a scribe, and specialists in process, operations, instrumentation and maintenance.
  2. Divide the process into nodes from the P&IDs (and the facility model), following changes of state or function.
  3. Describe the design intent of each node: nominal flow, pressure and temperature, and their limits.
  4. Select the relevant parameters and apply the guide words to generate deviations (for example MORE + pressure = overpressure).
  5. Identify the possible causes of each deviation.
  6. Identify the consequences, ignoring safeguards, to gauge the real hazard.
  7. List the existing safeguards (alarms, trips, relief valves, procedures) and rate the scenario if the approach calls for it.
  8. Issue recommendations for deviations that are not adequately controlled, with an owner and a due date.
Do not blindly combine every guide word with every parameter: the team keeps the combinations that are physically plausible for the node, otherwise the analysis drowns in irrelevant cases. Still record the discarded combinations briefly: it shows they were examined.

5Rating deviations

IEC 61882 does not require any rating: a HAZOP may stop at qualitative recommendations. In industry, however, each scenario is often rated for severity and probability on the site risk matrix, to rank the recommendations and flag scenarios for deeper analysis. The principles are those of the cross-cutting topic Rating a risk. The example below uses 1-to-4 scales (1 = negligible or very unlikely, 4 = catastrophic or frequent).

The consequence is assessed without the safeguards; the likelihood takes into account only those safeguards that are truly independent of the cause. Mixing the two leads either to underestimating the hazard or to counting the same barrier twice.

6Example: a reactor feed line

Node 1 (fictitious): transfer of toluene from tank T-101 to reactor R-201 by pump P-101, through control valve FV-101 and isolation valve XV-101. Design intent: 5 m³/h, 3 bar at the discharge, ambient temperature. Line design pressure: 10 bar; pump shut-off pressure: 6 bar.

#ParameterGuide wordDeviationCausesConsequencesExisting safeguards SPRecommendation
1FlowNONo flow to R-201 P-101 trip, XV-101 closed in error, plugged strainer Pump running dry, overheating and seal leak; production delay Low-flow alarm FAL-101 S2 P3 Automatic P-101 shutdown on very low flow
2FlowMOREFlow above 5 m³/h FV-101 stuck open, flowmeter drift R-201 overfilling, toluene overflow to the vent, fire risk High-level alarm LAH-201 (same sensor as the level control) S4 P2 Add an independent high-high level switch closing XV-101; scenario to be quantified by LOPA
3PressureMOREOverpressure at the discharge XV-101 closed with the pump running Pressure limited to 6 bar, below the design pressure (10 bar): no hazard, pump overheating Line design S1 P3 None: deviation covered by design
4FlowREVERSEBackflow from R-201 to T-101 P-101 stops while R-201 is at 2 bar Contamination of tank T-101 by the reaction mixture Check valve at P-101 discharge S3 P1 Add the check valve to the periodic test programme
5CompositionAS WELL ASWater in the toluene Insufficient tank-bottom drain after unloading Batch quality degraded, possible foaming in R-201 Product analysis on receipt S2 P2 Tank-bottom drain procedure before each transfer
HAZOP worksheet — “reactor feed” node, fictitious data (S = severity, P = probability)

Of the 5 deviations, line 2 clearly stands out (S4 × P2): its only safeguard is not independent of the cause, since the alarm uses the same sensor as the control loop. It is typically the scenario to pass on to a LOPA. Line 3 shows that a deviation can be closed without a recommendation, provided the reason is written down. This example is handled in Polyodos, from worksheet to Word report. See the Industrial risks demo or try Polyodos free for 30 days.

7Common mistakes

MistakeWhy it is a problem
Defining overly broad nodesA node covering a whole unit makes the parameters inconsistent (inlet pressure ≠ outlet pressure): node boundaries must follow changes in process state.
Confusing deviation and causeMORE FLOW is the deviation, “valve stuck open” is one of its causes: swapping them loses the guide word × parameter logic that makes the method powerful.
Working from out-of-date P&IDsHAZOP only analyses what is drawn: a facility modified since the last drawings partly escapes the study.
Crediting a safeguard that depends on the causeAn alarm sharing the sensor of the failed control loop does not protect against that failure: it must not reduce the likelihood.
Running the HAZOP alone, without a multidisciplinary teamThe method relies on combining viewpoints (process, instrumentation, operations) in session: performed alone, it loses much of its detection value.
Not following up recommendationsA recommendation without an owner or due date stays a dead letter; follow-up is part of the method.

8Further reading

Learn: the online courses Industrial risks and How to run an AI-assisted HAZOP on aurorisk.com.

Practise: the Industrial risks module user guide in Polyodos.

FR