1What is HAZOP?
HAZOP (HAZard and OPerability study) analyses a process node by node. For each node, it systematically applies guide words (NO, MORE, LESS, REVERSE, OTHER THAN…) to process parameters (flow, pressure, temperature, level…) to generate deviations from the design intent, then analyses their causes, consequences and existing safeguards.
Its strength is systematic coverage: combining guide word × parameter forces the team to examine drifts that free discussion might never raise (for example NO FLOW on a feed line). As its name says, it covers both hazards and operability problems (shutdowns, quality, operating difficulties).
2When to use HAZOP
- At the end of detailed design, once the piping and instrumentation diagrams (P&IDs) are stable enough: this is the classic time for a HAZOP.
- On an existing facility, during a periodic process safety revalidation.
- Before a process change, on the nodes affected.
- For batch processes, applying the guide words to the steps of a procedure rather than to lines.
HAZOP suits continuous fluid processes (chemicals, petrochemicals, pharmaceuticals, water treatment, energy). It is time-consuming: several weeks of sessions for a complex unit. For a first screening, a PHA is faster; to quantify the critical scenarios it identifies, HAZOP is often followed by a LOPA.
3Nodes, parameters and guide words
A node is a homogeneous section of the facility with a defined design intent (for example “feed line between pump P-101 and reactor R-201”). The parameters describe that intent: flow, pressure, temperature, level, composition, viscosity, time, sequence…
The basic guide words described in IEC 61882:
| Guide word | Meaning | Example deviation |
|---|---|---|
| NO / NOT | Complete negation of the intent | No flow |
| MORE | Quantitative increase | Pressure too high |
| LESS | Quantitative decrease | Temperature too low |
| AS WELL AS | Qualitative addition | Water present in the product |
| PART OF | Qualitative decrease | Component missing from a mixture |
| REVERSE | Logical opposite of the intent | Reverse flow |
| OTHER THAN | Complete substitution | Wrong product transferred |
For time and sequence deviations, add BEFORE / AFTER and EARLY / LATE, which are particularly useful for batch processes.
4HAZOP step by step
IEC 61882 divides the study into four phases: definition (scope, objectives, team), preparation (documents, node breakdown, schedule), examination (the sessions) and documentation and follow-up. The examination itself follows the loop below:
- Build the team: an independent facilitator (chair), a scribe, and specialists in process, operations, instrumentation and maintenance.
- Divide the process into nodes from the P&IDs (and the facility model), following changes of state or function.
- Describe the design intent of each node: nominal flow, pressure and temperature, and their limits.
- Select the relevant parameters and apply the guide words to generate deviations (for example MORE + pressure = overpressure).
- Identify the possible causes of each deviation.
- Identify the consequences, ignoring safeguards, to gauge the real hazard.
- List the existing safeguards (alarms, trips, relief valves, procedures) and rate the scenario if the approach calls for it.
- Issue recommendations for deviations that are not adequately controlled, with an owner and a due date.
5Rating deviations
IEC 61882 does not require any rating: a HAZOP may stop at qualitative recommendations. In industry, however, each scenario is often rated for severity and probability on the site risk matrix, to rank the recommendations and flag scenarios for deeper analysis. The principles are those of the cross-cutting topic Rating a risk. The example below uses 1-to-4 scales (1 = negligible or very unlikely, 4 = catastrophic or frequent).
6Example: a reactor feed line
Node 1 (fictitious): transfer of toluene from tank T-101 to reactor R-201 by pump P-101, through control valve FV-101 and isolation valve XV-101. Design intent: 5 m³/h, 3 bar at the discharge, ambient temperature. Line design pressure: 10 bar; pump shut-off pressure: 6 bar.
| # | Parameter | Guide word | Deviation | Causes | Consequences | Existing safeguards | S | P | Recommendation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Flow | NO | No flow to R-201 | P-101 trip, XV-101 closed in error, plugged strainer | Pump running dry, overheating and seal leak; production delay | Low-flow alarm FAL-101 | S2 | P3 | Automatic P-101 shutdown on very low flow |
| 2 | Flow | MORE | Flow above 5 m³/h | FV-101 stuck open, flowmeter drift | R-201 overfilling, toluene overflow to the vent, fire risk | High-level alarm LAH-201 (same sensor as the level control) | S4 | P2 | Add an independent high-high level switch closing XV-101; scenario to be quantified by LOPA |
| 3 | Pressure | MORE | Overpressure at the discharge | XV-101 closed with the pump running | Pressure limited to 6 bar, below the design pressure (10 bar): no hazard, pump overheating | Line design | S1 | P3 | None: deviation covered by design |
| 4 | Flow | REVERSE | Backflow from R-201 to T-101 | P-101 stops while R-201 is at 2 bar | Contamination of tank T-101 by the reaction mixture | Check valve at P-101 discharge | S3 | P1 | Add the check valve to the periodic test programme |
| 5 | Composition | AS WELL AS | Water in the toluene | Insufficient tank-bottom drain after unloading | Batch quality degraded, possible foaming in R-201 | Product analysis on receipt | S2 | P2 | Tank-bottom drain procedure before each transfer |
Of the 5 deviations, line 2 clearly stands out (S4 × P2): its only safeguard is not independent of the cause, since the alarm uses the same sensor as the control loop. It is typically the scenario to pass on to a LOPA. Line 3 shows that a deviation can be closed without a recommendation, provided the reason is written down. This example is handled in Polyodos, from worksheet to Word report. See the Industrial risks demo or try Polyodos free for 30 days.
7Common mistakes
| Mistake | Why it is a problem |
|---|---|
| Defining overly broad nodes | A node covering a whole unit makes the parameters inconsistent (inlet pressure ≠ outlet pressure): node boundaries must follow changes in process state. |
| Confusing deviation and cause | MORE FLOW is the deviation, “valve stuck open” is one of its causes: swapping them loses the guide word × parameter logic that makes the method powerful. |
| Working from out-of-date P&IDs | HAZOP only analyses what is drawn: a facility modified since the last drawings partly escapes the study. |
| Crediting a safeguard that depends on the cause | An alarm sharing the sensor of the failed control loop does not protect against that failure: it must not reduce the likelihood. |
| Running the HAZOP alone, without a multidisciplinary team | The method relies on combining viewpoints (process, instrumentation, operations) in session: performed alone, it loses much of its detection value. |
| Not following up recommendations | A recommendation without an owner or due date stays a dead letter; follow-up is part of the method. |